Dholera Developer & Project Rankings

Edition 2026.08 · Entry 11 of 33
Verified 4 August 2026

SHANTIBAN SKYLAR

2025
Registered 2025

This project is registered with the government. SEKSARIA BUILDCON LLP registered it with GujRERA, the Gujarat authority a builder must register with before selling anything, and the approval came through on 15 December 2025. Its registration number is PR/GJ/AHMEDABAD/DHOLERA/DSIRDA/MAA16212/151225/311229.

On the government record it covers 3,875.26 square metres of land and declares 157 units. On this site's score, which counts paperwork and nothing else, it comes 11 out of 33 with 90.0 out of 100 points.

What the record shows today: GujRERA holds a submission for all 2 quarters scheduled since registration, the declared completion date is 31 December 2029, the public application ledger carries no complaint row, and no other GujRERA registration is published on the promoter record.

Check this project on the government portalThe same record as raw dataBack to the full list

§01

How we know this project is in Dholera

A project can only appear on this site if its own government record ties it to Dholera. Here is the exact wording that does it for this one, copied from the record. Evidence tier: Official

  • RERA registration number contains taluka segment DHOLERA
  • RERA registration number contains authority segment DSIRDA
  • approvingAuthority on GujRERA record = 'Dholera Special Investment Region Development Authority'
  • GujRERA record subDistName (taluka) = Dholera
  • GujRERA record moje (village) = 'DHOLERA'
  • 'DHOLERA' appears in the GujRERA project address

Source: GujRERA project detail endpoint · Read 4 August 2026 · Status: OFFICIAL

§02

Everything the government record says

GujRERA registration record for SHANTIBAN SKYLAR, project id 29174, read 4 August 2026
FieldValue on the GujRERA record
Project nameSHANTIBAN SKYLAR
Promoter name as registeredSEKSARIA BUILDCON LLPGrouped on this exact string. This register merges no promoter names.
RERA registration numberPR/GJ/AHMEDABAD/DHOLERA/DSIRDA/MAA16212/151225/311229
GujRERA approval date15 December 2025The field GujRERA calls approvedOn, cross-checked against the registration application approval date.
Declared start date13 September 2025Promoter-declared. Status: TARGET.
Declared completion date31 December 2029 Date aheadPromoter-declared at registration. Status: TARGET, not an outcome.
Promoter-declared status at registrationNewNot a live construction status.
Project typeMixed Development
Land area under registration3,875.26 sq mGujRERA field totLandAreaForProjectUnderReg.
Project land areaBlank on the GujRERA pageGujRERA field totAreaOfLand. Where this is blank, the government page itself renders the line with no number.
Layout land area3,875.26 sq mGujRERA field totAreaOfLandLayout.
Total open area2,714 sq m
Total covered area1,161.26 sq m
Total carpet area7,450.75 sq mCarpet area as defined by the Real Estate (Regulation and Development) Act.
Declared units157 unitsInventory as declared: Flat (135), Shop (22).
DistrictAhmedabad
TalukaDholera
Village, the moje fieldDHOLERA
Registered addressDRAFT TOWN PLANNING SCHEME NO.2/B2, F P N O: - 15, NEW S.NO-87 AT DHOLERA, TAL-DHOLERA DIST: - AHMEDABAD.Reproduced verbatim from the record.
Approving authorityDholera Special Investment Region Development AuthorityReproduced with the spelling GujRERA publishes.
Record classOFFICIALRead from the GujRERA public portal. Nothing modelled, nothing estimated.
All areas in square metres, as published. Source: GujRERA per-project detail endpoint for project id 29174. Blank fields are printed blank because the government page is blank.

Source: GujRERA project detail endpoint · Read 4 August 2026 · Unit: square metres · Status: OFFICIAL

§03

Where the score came from, line by line

This project sits 11 of 33 with 90.0 out of 100 points. The table below shows every point it was given and every point it was not, so you can see which of the five tests it passed. Each one reads a field the government publishes. The full scoring rule is on the method page.

Register Standing Score components for SHANTIBAN SKYLAR, edition 2026.08
CriterionWhat it readAwardedOf
C1Registration evidenceEvidence tier OFFICIAL2020
C2Quarterly progress filing rate2 of 2 scheduled quarters carry a submission35.035
C3Declared completion date standingDeclared completion date 31 December 2029 still lies ahead2020
C4Complaint entries on the public ledger0 complaint entries on the public ledger1515
C5Promoter register depth0 other GujRERA registrations published on the promoter record010
Total awarded 90.0 of 100 available, normalised to 90.0 out of 100. Computed 4 August 2026.
§04

Has it been filing its quarterly updates

Every registered project owes the government a short progress update each quarter. This is the record of what was due and what arrived. It is a paperwork trail, not a construction report.

Quarterly progress filings for SHANTIBAN SKYLAR, as of 4 August 2026
MeasureValue
Quarters scheduled since registration2
Quarters with a submission2
Quarters without a submission0
Filing rate100.0%
Source: the GujRERA quarterly progress endpoint for this project. A filed quarter records a submission, not a stage of construction.

Source: GujRERA quarterly progress ledger · Read 4 August 2026 · Status: OFFICIAL

§05

Has anyone complained about it

The government publishes a ledger of complaints filed against each project. A complaint on that ledger means somebody filed one. It does not mean anyone has agreed with them, and the government does not publish what the complaint was about.

The GujRERA public application ledger carries no complaint row against this project as of 4 August 2026. That is a statement about the ledger on that date and not an endorsement of anything.

Source: GujRERA application ledger · Read 4 August 2026 · Status: OFFICIAL

§06

What else this builder has registered

The government record for this project also lists other registrations held by the same builder, wherever in Gujarat they are. It is a rough measure of how much this company has done through the formal route before.

GujRERA publishes no other registration on the promoter record for this project. That may mean the promoter holds none, or that the portal carries none against this record. The register prints what the endpoint returns and does not infer beyond it.

Source: GujRERA promoter history endpoint · Read 4 August 2026 · Status: OFFICIAL

§07

See this project next to the others

The same project sits in nine different orderings, and each one measures something else. Comparing across a few of them is more useful than reading any single rank.

If any figure on this page differs from the government record, the government record is right. Write to corrections@dholera-realestate.com with the registration number and the field, and the correction goes up on the changes page.